| Client |
Maersk Oil Qatar A.S. |
| Field |
Al Shaheen, Arabian Gulf. |
| Project |
Al Shaheen C Early Production
System. (1997–1998) |
| Scope |
Supply and operation of
a Mobile Offshore Production Unit, Cliffs
Drilling No.10, for the early production of
the Al Shaheen C wells. Production was from
a 12-well development, offshore Qatar, in
68 metres of water. Swire Production Testers
designed, converted, and mobilised the unit
from Galveston to Sharjah for final commissioning,
before installing it on location six months
from contract signing. |
|
|
| |
|
|
| |
|
|
| |
The system consisted of: |
|
| |
| • |
Cliffs Drilling No.10:
a Bethlehem Mat 250 converted into a MOPU
from a jack-up drilling rig. |
| • |
12-well riser/wellhead
deck support system (Texas Deck). |
| • |
60,000 bbl/day x 100MMscf/d
throughput capacity production process system. |
|
|
| |
|
|
| |
|
|
| |
The assets were owned or leased
by Swire Production Testers Limited and supplied
on a contract rental basis for two years. |
|
|
|